SIDEWALK CLOSURES AND CONSTRUCTION UPDATES AT THE FORMER MARYVILLE CONSTRUCTION SITE

To protect the public during demolition, a parking lane & the sidewalk at the north side of Montrose, east of Clarendon, will be closed from 2/21/17 through the week of 3/13/17. Additionally, a parking lane will be closed on the west side of Clarendon for deliveries starting 2/23 through 3/10. Signage will posted redirecting pedestrian traffic as needed.

The concrete crushing operations of the demolition rubble will be performed starting Friday 2/24 through 3/17/17. Dust control measures, as required per permit, will be in place.

Foundation work, beginning with installing steel piles, will be starting 2/24 and continuing until 3/31. This will cause some noise and ground vibrations in the surrounding area during pile driving operations, so please do not be alarmed.

The 46th Ward website provides you with the latest updates from JDL Development, please click here for more information.