Date: Friday, September 23, 2016 to Monday September 26, 2016
Work Hours: 9 PM to 4:00 AM (Continuous)
Work Activity: 3 Track – Cutover Weekend: Signal, Traction Power and track Work
Impact to Community:
Broadway, Wilson, and Leland will be closed, to vehicular traffic, during Construction Activities.
Broadway will re-open between 10 AM – 4 PM, on Saturday September 24th.
There will be some dust and noise
Howard-bound trains will not stop at Wilson, Lawrence, and Argyle stations.
For service to these stations, take a Howard-bound train to Berwyn and transfer to a 95th-bound train.
For service from these stations, take a 95th-bound train to Sheridan and transfer to a Howard-bound train.